Electricity Forum Intelligent Power Today Magazine Arc Flash Clothing

Transformer Testing & Maintenance



Case Study: Rapid Changes in Bushing Health

IntroductionContinuous online monitoring of bushings provides real-time information which can result in the early detection of a possible failure. Challenge: A Major AlarmA prominent U.S. utility was looking for a way to improve system reliability for their 138kV assets. They researched and...

Transformer Testing & Maintenance

transformer repair

Radiator Fin(s) Leak Repair

Radiator fins are notorious for leaking at various locations. One of which is where the fins are attached (welded) to the horizontal bottom-run header. Measurements are taken so a weir box can be installed to cover the fin(s) that are leaking. It is preferred the weir box will cover above the leaking area about 6".
This 6” cover will allow for urethane (poured into weir box) to adhere to the drier part of the fin(s) to assist with the sealing process. After pour, the technician will mark the outside of the weir box at the location(s) where the original leak was. This incase further work may be required for a better seal. After the urethane is poured and let to cure (usually overnight) the job is inspected to determined seal effectiveness. In the event we still have some leakage; whether the following day or later, an additional procedure may be performed. If leaking, the weir box is fabricated out of 11ga galvanized sheet metal which is thick enough for completing a 1/16" NPT. The technician will decide where (usually where it's been marked) and how many 1/16" D&T’s (drill & taps) are required. Once additional d&t's are completed, injection valves installed, then a special 2-part sealant (must be approved from a dielectric and DGA standpoint) will be injected. The thought is: now that there is cured urethane above the original leak(s) and we have marked the weir box for injecting close to that spot, we have created a bridging barrier for our sealant to back up against (so as not to extrude out the top of the weir box).

Related Articles


magazine_sep_oct_2023_article_3

Dielectric Voltage Testing – Standard Methods

There are two standard methods from ASTM International: D877, Standard Test Method for Dielectric Breakdown Voltage of Insulating Liquids Using Disk Electrodes, and D1816, Standard Test Method for Dielectric Breakdown Voltage of Insulating Oils of Petroleum Origin Using VDE Electrodes. VDE stands...

Insulation Resistance Test

Insulation Resistance (IR) test, often called Megger test, is more than 100 years old and assumed to be a very straightforward test. During my inspection and testing work in the past 15 years in Canada, US, and internationally, I have seen different practices of performing and interpretation of IR...

transformer oil regeneration

Transformer Oil Regeneration and Corrosive Sulfur

Enervac International ULC has been examining this issue for over 14 years with the help of our customers, mainly international power utilities, transformer manufacturers and transformer service companies. TRANSFORMER OIL REGENERATION PROCESSThe principal functions of the insulating fluid are to...


Page 1 of 9